Wakulla County, Florida
Verified record · verified September 17, 2026
Current status
discussion No data center ordinance has been adopted by Wakulla County.
What the governing body did
On June 15, 2026, the governing body voted to direct staff to draft an ordinance prohibiting data centers and to schedule and advertise the public hearings to consider adopting it, by a vote of 5–0. That action was direction to staff and authority to advertise; it was not adoption.
Pending final hearing
The final public hearing is on the governing body’s September 21, 2026 agenda, item 13:
Request Board Approval to Conduct the Final Public Hearing and Adopt an Ordinance Amending Section 2-4 of the Land Development Code Related to Definitions and Creating Section 6-40 of the Land Development Code to Prohibit Data Centers within the Unincorporated Areas of the County.
The hearing had not occurred as of the verification date shown above.
Primary source document
County minutes of the June 15, 2026 meeting, published by Wakulla County.
SHA-256 of the retained copy: aad88b8dbf7b940d3e00afcfe0536c71ec59a4742386ac5b311b9b5dfe8ee011
Scheduled
- September 21, 2026Item 13: Request Board Approval to Conduct the Final Public Hearing and Adopt an Ordinance Amending Section 2-4 of the Land Development Code Related to Definitions and Creating Section 6-40 of the Land Development Code to Proh...Agenda stored · Minutes not stored
Corrections and revisions
- September 17, 2026 · adoption pending datenone → 2026-09-21